  • Structural Demolition of platforms 12, 13, 14, 15.
  • Heritage canopy removal, cataloguing and storage.
  • Hazardous material removal and soil remediation.
  • Eastern Suburbs line: Structural demolition of suspended structures over rail corridor and public thoroughfares.
  • Soft strip of all aspects, staged to enable 24/7 operation of rail station.
  • Northern concourse – significant structural demolition.
  • Heritage salvage, underpinning and demolition of base of TCAC building including hydraulic jacking.
  • Significant excavation in complete isolation of the logistics route and surrounded by live rail environment, including significant saw cutting.
  • Escalator demolition.